Planning Redesign for an Industrial Controls Company with Global Operations

Project Summary: 

  • The goal was to improve the quality of the demand plans through Sales and Planning engagement and Statistical models 

  • The project revolved around three building blocks;  

Process diagnostics and recommendations to understand the lay of the land

Exception planning to focus on the key 20% of the products which make up 80% of the revenue 

Enable the many functionalities of SAP APO to improve planner productivity   

 

A broad overview of problems: 

  • Only one statistical model used for 10,000+ SKU’s.  
  • A generic model was run at the lowest level in weekly buckets producing the ubiquitous straight line. 
  • Demand Planning was getting Sales inputs in monthly buckets while the Planning platform allowed only weekly buckets 
  • Planners went through an elaborate excel process to reallocate and develop weekly plans. 
  • The process was severely handicapped by system limitations 

 

Developed a Distribution plan to deliver   

  • The Netted plan for deployment 
  • Feed the Transaction system where the Scheduling was done. 
  • Identify demand-supply imbalances
  • Issue alerts for the planners to address